General Enquiries 880-2-58616641-50
Home  /  Research

PUBLIC-PRIVATE/PRIVATE-PRIVATE PARTNERSHIP IN ACTION

1. Construction of Malek Chowdhury Academic Building for Bangladesh University of Health Science (BUHS) at Darus-Salam, Mirpur, Dhaka. (2nd phase: 1st floor to 5th floor)

Notifications of Award (NoAs) were issued at a cost of Tk.1795.28 lakh and Tk. 39.54 lakh for civil works and ancillary works, respectively for 1st floor to 5th floor of the said academic building under second phase. Structural works for 1st floor to 4th floor have already been completed.

2. Construction of Ibrahim Medical College (6th floor to 12th floor) over BIRDEM-2 at Segun Bagicha, Dhaka

The construction work is being done through PWD as a deposit work. Notification of Award (NoA) was issued to the selected contractor on 02.04.2012 at a cost of Tk. 1478.58 lakh for construction of 6th floor to 10th floor. Construction of the remaining two floors (11th and 12th floor) has been done through variations at a cost of Tk. 2943.49 lakh including civil, sanitary & electrification.

Structural works for 6th to 12th floor have already been completed. Necessary finishing works of the building are now in progress. The project is expected to be completed & handed over to competent authority very soon. A total of Tk. 2507.49 lakh was disbursed to PWD against the works upto June 2016.

3. Saima – Ibrahim Nursing College and Institute at Shafipur, Gazipur

sq. ft. has already been constructed for this institute and handed over to National Health Care Network (NHN). The ground floor and 1st floor of the building are being used as nursing college as planned originally. It has been designed to make temporary accommodation for the foreign faculties at the 3rd floor and hostel for the nurses at the 4th floor of the building; for which contractor has also been selected.

4. Establishment of a 50 bedded Diabetes, Endocrine and Metabolic Hospital for Women and Children at Uttara, Dhaka

The project is being implemented by BADAS in association with Department of Women Affairs under the Ministry of Women and Children Affairs. Government of Bangladesh (GoB) has approved the project with a total cost of Tk. 2399.59 lakh (GoB: Tk. 1439.75 lakh and BADAS: Tk. 959.84 lakh) The civil works of the project is being implemented through PWD as deposit work. The physical work of the project is in progress and estimated at 49 percent as on 30 June 2016. The project has incurred a cumulative expenditure of Tk. 920.00 lakh including BADAS land cost of Tk. 170.00 lakh upto 30 June 2016.

5. Establishment of a 100 Bedded Specialized Hospital in Comilla.

The project has been designed to establish a 100 bedded specialized hospital in Comilla with assistance from Government of Bangladesh. Total cost of the project is estimated at about Taka 2899.58 lakh. BADAS will implement the project in association with Department of Social Services (DSS) of GoB. The DPP of the project has already been submitted to the Planning Commission for approval.